Global 1 & 2 // Installation parts for cruise ships
July - December 2018
Project completed at...
100%
Holger steel
After long negotiations and order processing talks in Wismar, the order was booked for us. This large order is about the production and schedule monitoring in the cruise ship construction. Different suppliers in different countries have to be checked for adherence to delivery dates as well as quality. Global 1 and Global 2 are the largest cruise ships built in Germany to date. Here it is very important that the delivery dates are guaranteed for a smooth assembly process at the shipyard.
What are our tasks in this project?
- Deadline tracking for installations on cruise ships
- Coordination of supplier visits and their subcontractors
- Control of the suppliers for adherence to the delivery dates for the "Just in Time" assembly process at the shipyard.
This order is a fine example of good teamwork. Several parties are in the same boat and together delivery dates are realized.




Back
Go to